EPCC · FLAGSHIP
Flagship case studyKot Palak-1 Early Production Facility (EPF)
Flagship EPCC reference for Kot Palak-1 Early Production Facility — 50 MMSCFD sales gas at 950 PSIG, 2,500 BBL/day condensate stabilization, and multi-discipline construction for AEPL with DZR Energy in remote KPK.
- Client: Al-Haj Enterprises (AEPL) · DZR Energy (Dewan Petroleum)
- Location: Kot Palak Field, ~140 km off D.I. Khan, Khyber Pakhtunkhwa
- Value: ~USD 10 million
- Duration: 20 months (8 months EPCC + 12 months O&M)
- Capacity: 50 MMSCFD · 950 PSIG · 2,500 BBL/day condensate
Quantified execution metrics
Site gallery
Kot Palak-1 Early Production Facility is RISE’s signature upstream EPCC reference — a greenfield scope demonstrating integrated engineering, procurement, construction, and commissioning capability through operations transition.
The Al-Haj facility handles pressure boosting at 950 PSIG for a design flowrate of 50 MMSCFD to the sales gas tie-in pipeline, with condensate stabilization and processing of 2,500 BBL/day. RISE delivered quantified construction evidence including 18,350 inch-dia of piping, 202 field instruments, and 25 tons of structural steel.
Project delivery addressed remote location logistics, community sensitivity, and stringent HSE compliance — with dedicated mobilization of management, planning, QA/QC, HSE, civil, and operations staff alongside third-party certified equipment and operators.
RISE scope
- RISE acted as EPCC sub-contractor to DZR Energy for Al-Haj Enterprises (AEPL).
- Multi-discipline civil, mechanical, electrical, and instrumentation construction in a remote field location.
- Mobilization of manpower, equipment, and third-party certified operators for greenfield EPF delivery.
- Loop checking, hydrotesting, mechanical completion, commissioning, and O&M transition support.
Engineering deliverables
- Detailed engineering coordination and quantified deliverable sets
- Porta cabin camps, stores, mess halls, and site logistics
- Cranes, excavators, concrete equipment, and certified operator deployment
- Construction execution with stringent HSE compliance in a security-sensitive community environment
- Pictorial site documentation and operational handover packages